Sitework:

  • Tree doctor for existing trees onsite
  • Demo sidewalks
  • Demo curbs
  • Demo existing parking spaces
  • Remove shrubs existing
  • Strip topsoil in proposed disturbed areas
  • Grouting of existing Mobile site
  • Clay cap
  • Fill of site
  • Gas line installation to KIA eternal flame
  • Storm installation
    • Clean outs
    • Connection to Town storm sewer
  • Foundation excavation and pour:
    • Statue and memorial
    • Flag poles (casings)
    • Granite walls
  • Retaining wall installation:
    • Incorporate granite walls
    • Backfill retaining walls with topsoil
    • Plant trees and shrubs
    • Tree stakes and rope
  • Electrical installation:
    • Trenching
    • Light pole bases
    • Electrical install
    • Lighting installation
  • Prepare paving surfaces:
    • Subbase stone installation
  • Prepare concrete surfaces:
    • Subbase stone
  • Pour concrete surfaces (Sidewalks, steps, walkways)
  • Curb preparation:
    • Excavate and subbase stone
  • Pour curbs
  • Finalize paving subbase (fine grade)
  • Pave proposed parking lot:
    • Stripe lot
  • Prepare all paver areas:
    • Subbase stone
    • Sand
    • Brick installation
  • Prepare, furnish and install misc. items:
    • Information areas
    • Howitzer refurbishment
    • Flag pole installation
    • KIA Mother statue refurbishment
    • Names engraved on all granite slabs
    • Names engraved on all brick pavers
    • Installation of memorial emblems and statue
    • Benches throughout
  • Topsoil installation (4”)
  • Irrigation installation
  • Sod/ seed areas disturbed
  • Remaining landscape items to furnish and install:
    • Perennial plantings
    • Fabric
    • Mulch